IPv6 migration back to current platform (NZS,DBA,DBC) (Maintenance)
« Back
[#830] IPv6 migration back to current platform (NZS,DBA,DBC) (Maintenance)
Posted: 2019-08-19 10:34Start: 2019-09-09 07:00:00
End : 2019-09-23 10:03:00
Affects: IPv6 Traffic NZS, DBA, DBC
The planning is as following:
NZS: 9 to 12 September 2019
DBA: 16 to 19 September 2019
DBC: 23 to 26 September 2019
The migration will take on these days between 6:30 and 9:00.
Per datacenter we planned out 4 days:
Day 1: Preparation work, no downtime expected.
Day 2: Moving transit/upstream providers, no downtime expected.
Day 3: Moving customer IPv6, you may notice downtime of a few seconds.
Day 4: Reserved day to complete the remainder of the work if maintenance cannot be completed within the first 3 days.
Update 2019-09-11 9:50:
Maintenance on NZS is completed.
Update 2019-09-17 15:00:
Maintenance on DBA is completed.
Update 2019-09-23 10:03:
Maintenance on DBC is completed early.