IPv6 migration back to current platform (NZS,DBA,DBC) (Maintenance)

« Back

[#830] IPv6 migration back to current platform (NZS,DBA,DBC) (Maintenance)

Posted: 2019-08-19 10:34

Start: 2019-09-09 07:00:00
End : 2019-09-23 10:03:00

Affects: IPv6 Traffic NZS, DBA, DBC

As the new firmware is running stable for the past weeks, we will be migrating back to the current platform to restore redundancy to IPv6.

The planning is as following:
NZS: 9 to 12 September 2019
DBA: 16 to 19 September 2019
DBC: 23 to 26 September 2019

The migration will take on these days between 6:30 and 9:00.

Per datacenter we planned out 4 days:
Day 1: Preparation work, no downtime expected.
Day 2: Moving transit/upstream providers, no downtime expected.
Day 3: Moving customer IPv6, you may notice downtime of a few seconds.
Day 4: Reserved day to complete the remainder of the work if maintenance cannot be completed within the first 3 days.

Update 2019-09-11 9:50:
Maintenance on NZS is completed.

Update 2019-09-17 15:00:
Maintenance on DBA is completed.

Update 2019-09-23 10:03:
Maintenance on DBC is completed early.