Generator maintenance Equinix-AM5 (Maintenance)

« Back

[#779] Generator maintenance Equinix-AM5 (Maintenance)

Posted: 2019-03-26 07:10

Start: 2019-04-29 07:00:00
End : 2019-04-29 18:00:00

Affects: Equipment located at Equinix-AM5

We received a maintenance notification from one of our infrastructure datacenters Equinix-AM5 that they are having maintenance on generator C.

Their exact maintenance reason is:

Please be advised that Equinix will be performing preventive maintenance on generator C.

Only one generator will be maintained at a time, generator F will be placed back in service before maintenance commences on the next one.

No loss of resilience is expected with "N+1" redundancy maintained during this period and all cabinet supplies remaining UPS backed.

Additional there will also be performed a generator load test. This is a routine test of the generator which will be performed in a controlled manner,
during the test customer load will be transferred from Utility to Generator.

their reference is 5-186079286285